SHORTCUTS TO SOLVE TIME & WORK:HOW TO SERIES
Want to Become a Bank, Central / State Govt Officer in 2020?
Join the Most awarded Coaching Institute & Get your Dream Job
Now Prepare for Bank, SSC Exams from Home. Join Online Coure @ lowest fee
Lifetime validity Bank Exam Coaching | Bank PO / Clerk Coaching | Bank SO Exam Coaching | All-in-One SSC Exam Coaching | RRB Railway Exam Coaching | TNPSC Exam Coaching | KPSC Exam Coaching
SHORTCUTS TO SOLVE TIME & WORK:HOW TO SERIES
Hi Bankersdaily Aspirants,
There is exactly 10 days for our IBPS RRB Prelims Examination,this is the most important time for our career & from our side we are giving full support for all the aspirants.For the Beginners we had started Learn Series & it went well without any hurdle .If you are beginner & you hadn’t look into Learn Series,Check now because we had discussed all the basic concepts in both Aptitude & Reasoning Section
INTRODUCTION:
Friends today we came with,new problems on Time & Work,As you all think Time & Work is not that much tough if we know the shortcuts and the relationship between the terms in time & work.We had already discussed Basic Concepts in Time & Work before looking into Problems Let us look into Basic Concept in Time & Work.
1)24 men can complete the piece of work in 16 days at the same time 32 men can complete the same work in 24 days.If 16 men & 16 women work together for 12 days.Find how men should be added if the remaining work should be completed in 2 days?
Given that,
24 Men can Complete the work in 16 days
32 Men can Complete the work in 24 days
16 Men + 16 Women work together for 12 days,
Remaining 1/4 th of the work is to be completed with the help of additional men
From this we found that the number of Men=40
But initially there are 16 men working So Additional Men required is 40-16=24 Men
Therefore,we need 24 Men additionally to complete the work.
Friends we found the answer,
Do you think Can we crack the exam if we use this method to solve these kinds of Problems?
Then My Answer would be BIG NO,It is waste of time since we have to answer 100 questions in 1 hour,So let us look the Alternate Method to solve these kinds of Problems,This is Quite Easy compared to the above method,
Efficiency is Work done by an individual or a group in 1 day
Efficiency=Work done/Number of Days Taken
What is Given in the Question?
24 Men can Complete the work in 16 days
The same work,
32Women can Complete the work in 24 days
Total Work=LCM(384,768)=768
Efficiency of Men=768/384=2 work/day
Efficiency of Women=768/768=1 work/day
Therefore 16 Men +16 Women work for 12 days
Then they would complete,
=(16*2+16*1)*12
=(32+16)*12
=48*12
=576 Work
So when they work for 12 days they would complete 576 Work
Remaining Work=768-576=192 work
In this 192 Work 16 Women will complete 32 Work(Since 16 women can Complete 16 work per day therefore for 2 days they will complete 16*2=32 work)
Therefore Remaining Work=192-32=160work
160 has to be completed by Men alone
=160/2*2(2 days and Efficiency of 1 man =2,So only we had written 2*2)
=160/4
=40 Men
There is already 16 Men So we need 40-16-24 Men
Friends I think you found my alternate Method as easier & I just Explained in detail because you just want to understand the concept or else this sum can be solved in just 3 steps.You can also solve this problem in just three steps if you practice well,So Practice this sum.
Is this Article is helpful?
If Yes then share what you learned with your friends.Because “KNOWLEDGE GROWS WHEN YOU SHARE”
If you have any query don’t hesitate to ask your doubt,we are here to help you at any time Post your Query in our Comment box so that we may know it.